Solar outshines nuclear power plants

Share

Credit score: Pixabay/CC0 Public Area

Between now and 2050, the Worldwide Power Company initiatives that greater than $100 trillion will probably be spent on constructing net-zero power infrastructure globally. But each single certainly one of these initiatives runs the chance of higher-than-expected development prices or time delays. Newer applied sciences launched up to now decade, reminiscent of hydrogen or geothermal power, are much more tough to judge as authorities businesses, power builders, utilities, traders, and different stakeholders resolve which sustainable power programs are greatest for future initiatives.

In a brand new state-of-the-art examine, published within the journal Power Analysis & Social Scienceresearchers on the Boston College Institute for International Sustainability (IGS) have discovered that runaway development prices and delayed timelines stymie many power initiatives. The truth is, the typical venture prices 40% greater than anticipated for development and takes nearly two years longer than deliberate, because the examine confirmed.

Nuclear energy vegetation are the worst offenders, with a mean development value overrun usually twice as a lot as anticipated or extra, and probably the most excessive time delays. To be actual, the typical nuclear energy plant has a development value overrun of 102.5% and finally ends up costing $1.56 billion greater than anticipated.

Taking a look at newer net-zero choices reveals increased threat as nicely. Hydrogen infrastructure and carbon seize and storage each exhibit vital common time and price overruns for development, together with thermal energy vegetation counting on pure fuel, calling into query whether or not these may be scaled up shortly to satisfy emission discount targets for local weather mitigation.

“Worryingly, these findings raise a legitimate red flag concerning efforts to substantially push forward a hydrogen economy,” says Benjamin Sovacool, lead and first writer of the examine, director of IGS, and professor of Earth and setting.

Against this, solar energy and electrical energy grid transmission initiatives have the very best development observe report and are sometimes accomplished forward of schedule or beneath anticipated value. Wind farms additionally carried out favorably within the monetary threat evaluation.

For Sovacool, the proof is obvious: “Low-carbon sources of energy such as wind and solar not only have huge climatic and energy security benefits, but also financial advantages related to less construction risk and less chance of delays,” he says. “It’s further evidence that such technologies have an array of underrated and underappreciated social and economic value.”

Utilizing an authentic dataset considerably bigger and extra complete than present sources, the examine supplies probably the most rigorous comparative evaluation of development value overrun dangers and time delays for power infrastructure initiatives globally.

The researchers compiled knowledge on 662 power infrastructure initiatives masking a various spectrum of expertise lessons and capacities, constructed between 1936 and 2024 throughout 83 international locations, representing $1.358 trillion in funding. This contains rising improvements reminiscent of geothermal and bioenergy, offering contemporary insights into the associated fee dynamics of those not too long ago commercialized applied sciences.

In whole, the examine evaluated ten varieties of initiatives: thermoelectric energy vegetation fueled by coal, oil, or natural gas combustion; nuclear reactors; hydroelectric dams; utility-scale wind farms; utility-scale photo voltaic photovoltaic and concentrated solar energy services; high-voltage transmission traces; bioenergy energy vegetation; geothermal energy vegetation; hydrogen manufacturing services; and carbon capture and storage services.

Understanding what causes power initiatives to go over finances and fall not on time—and when that tipping level happens—is one other vital contribution of this world evaluation. The examine examined diseconomies of scale, construction delays, and governance elements to establish important thresholds when venture prices surge, serving to to tell higher threat administration methods.

“I’m particularly struck by our findings on the diseconomies of scale, with projects exceeding 1,561 megawatts in capacity demonstrating significantly higher risk of cost escalation,” says Hanee Ryu, second and corresponding writer and a visiting researcher at IGS. “This suggests that we may need to reconsider our approach to large-scale energy infrastructure planning, especially as we commit trillions to global decarbonization efforts.”

What this might imply, Ryu explains, is that smaller, modular renewable initiatives may not solely deliver environmental advantages, but additionally probably cut back monetary threat and provide higher finances predictability.

Extra data:
Benjamin Okay. Sovacool et al, Past economies of scale: Studying from development value overrun dangers and time delays in world power infrastructure initiatives, Power Analysis & Social Science (2025). DOI: 10.1016/J. OSS.2025.104057

Supplied by
Boston University


Quotation:
Weighing funding threat for power infrastructure development: Photo voltaic outshines nuclear energy vegetation (2025, Could 19)
retrieved 19 Could 2025
from https://techxplore.com/information/2025-05-investment-energy-infrastructure-solar-outshines.html

This doc is topic to copyright. Other than any honest dealing for the aim of personal examine or analysis, no
half could also be reproduced with out the written permission. The content material is supplied for data functions solely.



Our Main Site

Read more

More News